So much seems to have happened since we started building unfortunately most of the work is hidden under concrete. I'll try and show you how things have progressed with a few photos (which is code for 'I'd better write this down for myself or I'm going to forget all the work that has been done before the first invoice arrives').

Earth from the areas where the two extensions are being built was excavated and then the foundations dug and filled with concrete

Digging the levels for the smaller extension
Stone has been poured into the barn as a sub-base to the floor, this was leveled using a laser level ready for the next process.
Layer of stone throughout the floor
 Blockwork has been built up on top of the foundation, this essentially forms a large tray for reinforced concrete to be poured onto the damp proof course.
Blockwork for the larger extension
So after the stone was leveled (are you asleep yet?) sand was added and leveled then the DPC was put in place with steel rods on top to give the floor plenty of strength.
Grey sand, red DPC and steel, the blue pipe is where the mains water comes into the building, the brown pipe is where the sewerage leaves the building
 Concrete was poured over the steel reinforcements, it involved 3 loads to get the entire area poured.
A big cement mixer pouring the concrete

Kev getting the concrete levels just right

Our lovely new floor ready for insulation, underfloor heating, screed, then tiles.
So that is the internal groundworks completed, (and by my calculations you should be just about to nod off) all that's left for the groundworks is to run some drainage around the building, install a rainwater harvesting tank and a sewerage treatment plant with a discharge pipe that will run treated water 300m to a nearby stream. Some of this work will be done in Spring when conditions should be more favourable.

We anticipate the actual building work to begin after Christmas, hopefully the worst of the mess and mud will be over by then. As you can imagine caravans and muddy shoes are a bit of a pain. Speaking of caravans, the wood burner is cranking out some lovely heat and we're still enjoying the scenery...

Just before sunrise
Always sunny in Kernow

Just before sunset

Tuesday, 9 November 2010

Multimedia Magic

Wow, now we're getting technical... here is a short tour of the barn so far!

Friday, 5 November 2010

Rapid Progress


The ground-works guys from Michael Vanstone's are doing a good job. We now have a temporary driveway so that we can receive deliveries and drive cars across the garden to our caravan. The location of the drive is pretty much where the finished drive will be built.
New Driveway

Underpinning has gone as well as anyone could hope, a solid clay base is ideal for the walls to sit on but it's fairly easy to excavate with a mini digger. The mini digger conveniently fits inside the barn so this saves a lot of time and energy and creates a nice dry site for the builders to work within.
Shuttering securing concrete below the barn wall
 
Concrete underpinning completed in sections, eventually most of the earth sections will be excavated and replaced with concrete. It takes four days for the concrete to set.
Part of the barn wall has been demolished, this will allow the floor in the extension to be poured at the same time as the barn floor creating one solid slab of concrete.
A rather large hole in the barn. The foundations for the extension (lounge area) are being dug out by the digger on the left of picture.


This gable end will have a small extension too. It will accommodate a small shower room and utility area